Roman Mtn Coal Mine

Canada / British Columbia / Tumbler Ridge /
 coal mine  Add category
 Upload a photo

The Roman Mountain project, located immediately south of the current Trend Mine, envisages an open pit mine producing up to 3 million tons of coal per annum with a life expectancy of about 10 years. The Trend and Roman mining operations will be integrated and utilize as much of the existing infrastructure as possible. Additional plant capacity and mining equipment will be required in order to achieve full production. A prefeasibility study will be completed in 2010; the Environmental Assessment report will be submitted in early 2010. Mining is envisaged to commence in 2013, with full production being achieved later in that year.



peacerivercoal.com/aboutus.html
Nearby cities:
Coordinates:   54°53'2"N   120°58'10"W
This article was last modified 15 years ago