Pomeroy Wind Farm is located in a roughly rectangular area stretching about 8 miles west and 6 miles north of Pomeroy, Iowa. It is actually registered as 4 wind farms, called Pomeroy I, Pomeroy II, Pomeroy III and Pomeroy IV.:
• Pomeroy I was constructed in 2007 and contains 82 GE Energy 1.5sle turbines with a combined nominal capacity of 123 MW.
• Pomeroy II was constructed in 2007 and contains 50 GE Energy 1.5sle turbines with a combined nominal capacity of 75 MW.
• Pomeroy III was constructed in 2008 and contains 39 GE Energy 1.5sle turbines with a combined nominal capacity of 58.5 MW.
• Pomeroy IV was constructed in 2011 and contains 13 Siemens SWT-2.3-101 turbines with a combined nominal capacity of 29.9 MW.
In total, these 4 Pomeroy wind farms contain 184 wind turbines with a nameplate capacity of 286.4 MW.
On the ground, the individual turbines for phases I, II & III are intermingled with each other, although Pomeroy III's turbines are generally to the west and north. I have not been able to distinguish between phases I and II. The 13 turbines of Pomeroy IV are all located south of the railway between Pomeroy and Fonda.
• Pomeroy I was constructed in 2007 and contains 82 GE Energy 1.5sle turbines with a combined nominal capacity of 123 MW.
• Pomeroy II was constructed in 2007 and contains 50 GE Energy 1.5sle turbines with a combined nominal capacity of 75 MW.
• Pomeroy III was constructed in 2008 and contains 39 GE Energy 1.5sle turbines with a combined nominal capacity of 58.5 MW.
• Pomeroy IV was constructed in 2011 and contains 13 Siemens SWT-2.3-101 turbines with a combined nominal capacity of 29.9 MW.
In total, these 4 Pomeroy wind farms contain 184 wind turbines with a nameplate capacity of 286.4 MW.
On the ground, the individual turbines for phases I, II & III are intermingled with each other, although Pomeroy III's turbines are generally to the west and north. I have not been able to distinguish between phases I and II. The 13 turbines of Pomeroy IV are all located south of the railway between Pomeroy and Fonda.
Nearby cities:
Coordinates: 42°35'36"N 94°45'21"W
- Highland Wind Farm 99 km
- Rolling Hills Wind Farm 145 km
- Pleasant Valley Wind Farm 209 km
- Prairie Breeze I Wind Farm 295 km
- Bishop Hill I Wind Farm 400 km
- Bison Wind Farm 744 km
- Brady I Wind Energy Center 795 km
- Blackspring Ridge Wind Farm 1630 km
- Shepherds Flat Wind Farm 2047 km
- Windy Point/Windy Flats wind farm 2107 km
- Sunken Island Lake 12 km
- Sunken Grove State Game Management Area 12 km
- Manson crater 17 km
- Pocahontas Municipal Airport (POH/KPOH) 19 km
- Gilmore City, Iowa 30 km
- Pickeral Lake 37 km
- Ottosen, Iowa 46 km
- Silver Lake 50 km
- Section 23, Riverdale Township, Kossuth County, Iowa 58 km
- Ambrose A. Call State Park 65 km