Kakula Decline Shaft
Congo (Dem. Rep.) /
Katanga /
Kolwezi /
World
/ Congo (Dem. Rep.)
/ Katanga
/ Kolwezi
mine, copper mine, mine shaft
This is the boxcut for the two parallel decline shafts that will dip at -8.5°, one for personnel and machinery and the other for a conveyor. Both shafts measure 5.5 m wide x 6.0 m high and are spaced 20 m apart. Every 100 m down decline, a 20 m cross-cut between the drives and twin remuck cubbies are required.
The Kakula box cut was successfully completed on October 26, 2017, and the first blast for the twin declines at Kakula took place on November 16, 10 days ahead of schedule. The Contractor for the shafts is JMMC, a DRC subsidiary of JCHX Mining Management of Beijing, China. Depending on ground conditions, the 3,600-metre decline development contract is scheduled for completion in approximately one year.
The Kakula box cut was successfully completed on October 26, 2017, and the first blast for the twin declines at Kakula took place on November 16, 10 days ahead of schedule. The Contractor for the shafts is JMMC, a DRC subsidiary of JCHX Mining Management of Beijing, China. Depending on ground conditions, the 3,600-metre decline development contract is scheduled for completion in approximately one year.
Nearby cities:
Coordinates: 10°53'18"S 25°11'30"E
- Centrale Shaft South 12 km
- Centrale Decline North 13 km
- Zondereinde Platinum Mine 1560 km
- Phalaborwa Copper Mine 1582 km
- Kroondal Platinum Mine 1653 km
- Cullinan Diamond Mine 1679 km
- ERPM Gold Mine 1733 km
- Koornfontein Coal Mine - Blinkpan Underground 1749 km
- Deelkraal South Property 1750 km
- Petra Diamonds - Kimberley 1989 km
- Kakula Resource Area 4.4 km
- Kamoa Permit 13025 5.7 km
- Kamoa Permit 12873 7.3 km
- Kamoa Resource Area 13 km
- Kalongwe Copper Project 15 km
- Kamoa Permit 13026 17 km
- Bwabwati 28 km
- Kalene Hill (Mission) 114 km
- Kalene Hill 114 km
- Etang Lutembwe 117 km