Punatsangchhu-I Hydro Electric Project MC2
Bhutan /
Wangdue Phodrang /
Bajo /
World
/ Bhutan
/ Wangdue Phodrang
/ Bajo
hydroelectric power station
Add category
Construction of Head Race Tunnel from ADIT-I & ADIT-II
Contractor: Gammon India Ltd.
Date of Start: 26th April 2009
Date of Completion: 26th April 2014
Contractor: Gammon India Ltd.
Date of Start: 26th April 2009
Date of Completion: 26th April 2014
Nearby cities:
Coordinates: 27°23'54"N 89°54'17"E
- Gadarwara Super Thermal Power Plant 1223 km
- Balimela Dam Reservoir 1277 km
- POLAVARAM MULTIPURPOSE IRRIGATION PROJECT 1410 km
- Mangla Dam 1688 km
- Tarbela Dam 1805 km
- Ghazi-Barotha Hydropower Project 1833 km
- Pavana Dam 1944 km
- Talakalale Balancing Reservoir 2151 km
- Chakra Reservoir Lake 2164 km
- Roghun Hydroelectric Dam Project Site 2254 km
- Bjimthangkha Colony 2 km
- Gasetsho Gom 3.1 km
- JIBA Gyalsung Project Khotokha 6.7 km
- Jatshoka 10 km
- Tencholing MTC (military training center) 10 km
- College of Natural Resources - Royal University of Bhutan 12 km
- Marlung 13 km
- Sabcheekha 14 km
- Paglo 14 km
- Punakha Dzongkhag 30 km