New Central Jail or ‘Correctional Home’ (Phase I) inaugurated by Goa Chief Minister
Laxmikant Parsekar on 30th May 2015 at Colvale Goa.
Phase I which is about 80% of the total project cost about Rs. 72 crores (of the estimated cost 107.72 of whole project, area 2,25,034 sq mts,). I think the work on the project started in the year 2010. The first phases consist of three barracks – two of which will be used to house the prisoners (see Convicts block / under Trial Block), staff quarters, kitchen, administrative block, 15-bedded hospital and a dental unit
Soon, all the inmates of Central Jail Aguada, Mapusa and few from Sada will be shifted here..
Remaining work, they say will be completed within 8-9 months or by March 2016.
Earlier, the project missed several (completion) dates and the matter was even referred to the court.
Stats:
- Currently, the capacity of the Jail is around 300 but when fully completed it can accommodate upto 624 prisoners.
- The present strength of Prisoners all over Goa is about 550 of which about 120 are convicts
Here is video www.youtube.com/watch?v=tB8_xP3jugM