NLEX Connector


NLEX Connector (North Luzon Expressway Connector), also known as the NLEX–SLEX Connector Road (North Luzon Expressway–South Luzon Expressway Connector), NLEX Connector Road, and NLEX Segment 11 during the planning stages, is a 7.7-kilometer (4.8 mi), four-lane elevated expressway in Metro Manila, Philippines. It connects the NLEX Harbor Link to the Metro Manila Skyway, which in turn connect to the North and South Luzon Expressways, respectively, while traversing parallel to the PNR Metro Commuter Line. The highway has five interchanges, four of which is currently operational. Alongside NLEX Harbor Link, trucks are allowed to use it.

Construction began in 2019 and was partially opened in March 2023. Its remaining section up to Santa Mesa is under construction.

Project Cost
P 15.743 B – Construction Cost
P 7.459 B – Right-of-Way Cost
P 0.100 B – Relocation of Utilities
P 23.302 B – Total Project Cost

The project with an accomplishment of 8.96% is behind by schedule by 7.72%. This is due to lockdown brought by the Covid-19 pandemic.
Nearby cities:
Coordinates:   14°37'11"N   120°59'23"E
This article was last modified 8 months ago