Punatsangchhu-II HEP Project C1 (Dam)
Bhutan /
Wangdue Phodrang /
Bajo /
World
/ Bhutan
/ Wangdue Phodrang
/ Bajo
hydroelectric power station/plant
Add category
Construction of Diversion Tunnel, Dam, Intake.
Client: Punatsangchhu Hydroelectric Project Authority
Contractor: Jaiprakash Associates Ltd. [Noida, India}
Date of Start: July 25, 2011
Completion Period: 66 months
Date of Completion: January 24, 2017.
Client: Punatsangchhu Hydroelectric Project Authority
Contractor: Jaiprakash Associates Ltd. [Noida, India}
Date of Start: July 25, 2011
Completion Period: 66 months
Date of Completion: January 24, 2017.
Nearby cities:
Coordinates: 27°18'45"N 89°57'6"E
- Upper Tamakoshi Hydropower project 376 km
- Gadarwara Super Thermal Power Plant 1223 km
- Balimela Dam Reservoir 1272 km
- POLAVARAM MULTIPURPOSE IRRIGATION PROJECT 1405 km
- Mangla Dam 1696 km
- Tarbela Dam 1813 km
- Ghazi-Barotha Hydropower Project 1841 km
- Pavana Dam 1944 km
- Talakalale Balancing Reservoir 2148 km
- Chakra Reservoir Lake 2162 km
- Menphunang 7.9 km
- Taagsha 15 km
- Haytsho 23 km
- Himtsho 23 km
- Ugpathangkha 25 km
- Atsephoog 25 km
- Jatsho 25 km
- Chhuchhepangkha 26 km
- Dagana Dzongkhag 37 km
- Chhukha Dzongkhag 52 km