HERE L&T WORK FOR SOONGO SONGO PROJECT. ELECTRICAL CONTRACTOR - CEIL & INSTRUMENTATION CONTRACTOR WAS AARKAY INSTRUMENTS P. L. (INDIA-MUMBAI). THISPROJECT IS OF COLLECTING GAS FROM 5 WELLS AT THIS ISLAND. CLEAN IT & SEND TO TANZANIA MAIN LAND THROUGH CROSS COUNTRY PIPE LINE. PIPE LINE WORK IS DONE BY L&T ECC. THIS LINE GOES TO UBUNGO POWER PLANT FOR POWER GENERATION. FOR L&T ECC E&I JOB DONE BY AARKAY INSTRUMENTS.