Huntorf CAES Plant

Germany / Niedersachsen / Berne / Große Hellmer
 power station, energy storage
 Upload a photo

First commercial CAES plant, operational since 1978, using nuclear-sourced night-time power to compress and inject the air into two caverns of 310,000 m³ total volume. The 600 m cavern depth ensures the air's stability through seasonal temperature changes, and guarantees the specified maximum pressure of 100 bar. One cavern is cycled daily; the other serves as backup when the nearby nuclear power plant goes offline
Nearby cities:
Coordinates:   53°11'23"N   8°24'30"E
  •  6.5 km
  •  18 km
  •  47 km
  •  107 km
  •  121 km
  •  129 km
  •  175 km
  •  262 km
  •  278 km
  •  295 km
This article was last modified 4 years ago