This is the Twickenham Platinum Mine Mining Right and it is owned and operated by Anglo Platinum. It currently has 2 active shafts, the Twickenham Shaft and the Hackney Shaft.
SAFETY
Twickenham achieved zero fatalities during the year. The lost-time injury-frequency rate for the year, however, deteriorated from 0.60 in 2007 to 1.77 in 2008.
PRODUCTION
Equivalent refined platinum ounces increased by 2% to 9,500 ounces in 2008, compared with 9,300 ounces in 2007. The average 4E built-up head grade increased to 4.76 g/t in 2008, from 4.65 g/t in 2007. Twickenham Platinum Mine is a 100% UG2 operation.
COSTS
Total cash on-mine costs increased by R69 million or 54% to R197 million. The cash onmine cost per equivalent refined platinum ounce increased by 50% to R20,706 per ounce, compared with R13,763 in 2007. The cost per tonne milled increased by 49% to R1,203.
CAPITAL EXPENDITURE
Total capital expenditure was R517 million in 2008, compared with R168 million in 2007.
PROJECTS
The mining training centre, which is an underground mine development centre for the Eastern Limb expansions at Twickenham shaft, was approved in the second quarter of 2007 and is progressing well. The R7.1 billion Twickenham expansion project was approved by the Board in quarter one of 2008. The project is scheduled to produce in the fourth quarter of 2012. Financial constraints arising from the global economic downturn have slowed the project down by six months.
OUTLOOK
Production from the Twickenham mini-mine will continue in 2009 and a toll concentrating agreement will be entered into with Lebowa to treat ore from Twickenham. This arrangement will be reviewed at the time when Anooraq Resources assumes management control over Lebowa.
Reference for information:
www.angloplatinum.com/business/operations/twickenham_se...
angloplatinum.investoreports.com/angloplatinum_sdr_2008...
SAFETY
Twickenham achieved zero fatalities during the year. The lost-time injury-frequency rate for the year, however, deteriorated from 0.60 in 2007 to 1.77 in 2008.
PRODUCTION
Equivalent refined platinum ounces increased by 2% to 9,500 ounces in 2008, compared with 9,300 ounces in 2007. The average 4E built-up head grade increased to 4.76 g/t in 2008, from 4.65 g/t in 2007. Twickenham Platinum Mine is a 100% UG2 operation.
COSTS
Total cash on-mine costs increased by R69 million or 54% to R197 million. The cash onmine cost per equivalent refined platinum ounce increased by 50% to R20,706 per ounce, compared with R13,763 in 2007. The cost per tonne milled increased by 49% to R1,203.
CAPITAL EXPENDITURE
Total capital expenditure was R517 million in 2008, compared with R168 million in 2007.
PROJECTS
The mining training centre, which is an underground mine development centre for the Eastern Limb expansions at Twickenham shaft, was approved in the second quarter of 2007 and is progressing well. The R7.1 billion Twickenham expansion project was approved by the Board in quarter one of 2008. The project is scheduled to produce in the fourth quarter of 2012. Financial constraints arising from the global economic downturn have slowed the project down by six months.
OUTLOOK
Production from the Twickenham mini-mine will continue in 2009 and a toll concentrating agreement will be entered into with Lebowa to treat ore from Twickenham. This arrangement will be reviewed at the time when Anooraq Resources assumes management control over Lebowa.
Reference for information:
www.angloplatinum.com/business/operations/twickenham_se...
angloplatinum.investoreports.com/angloplatinum_sdr_2008...
Nearby cities:
Coordinates: 24°26'22"S 30°2'12"E
- Modikwa Platinum Mine 9 km
- Bokoni Platinum Mine 36 km
- Tamboti Platinum Project 47 km
- Booysendal Platinum Mine 70 km
- Mogalakwena Platinum Mine 134 km
- Waterburg Project 190 km
- Evander Gold Mine 241 km
- East Rand Mining Operations 258 km
- Consolidated Modderfontein Gold Mine 259 km
- Nigel Gold Mine 260 km
- Havercroft Andalusite Mine 21 km
- Annesley Andalusite Mine 23 km
- Bewaarkloof Nature Reserve 39 km
- Noodhulp Study Area 49 km
- Lebowakgomo 56 km
- Tzaneen Dam Reservoir 72 km
- Consolidated Murchison Mine 90 km
- Xihoko Village - Nyavane 99 km
- Ntshuxi village 135 km
- Kruger National Park 155 km
Comments